DOVE at L and T Realty Elixir Reserve, Chandivali

by Larsen & Toubro Ltd. (Realty Division) · Chandivali, Mumbai 400072 · Map

Launched
Apr 20244 yrs 4 mths promised
Possession (MahaRERA)
Aug 2028Not extended
Concrete structure
100%Nearing possession
Booked
103 of 13974% · 98 in Jul 2026
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
72
4 BHK
52
Other units
15
Total units
139
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 41%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%103
100%41%0%98
100%0%0%91
0%0%0%74

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

DOVE at L and T Realty Elixir Reserve by Larsen & Toubro Ltd. (Realty Division) (L&T Realty) is a 139-unit BMC-sanctioned project in Chandivali, Mumbai 400072, launched in April 2024 with possession due in August 2028. 103 units booked out of total 139 units. The concrete structure (RCC) is complete.

Read full summary

DOVE at L and T Realty Elixir Reserve is a BMC-sanctioned project by Larsen & Toubro Ltd. (Realty Division) in Chandivali, Mumbai 400072, registered with MahaRERA as P51800055488. It was launched in April 2024. It has 139 units in 1 building: 124 homes (3 and 4 BHK) and 15 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is August 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.

103 units booked out of total 139 units (74%). Since the July 2026 update, 5 more units have been booked and the reported concrete structure (RCC) has gone from 41% to 100%.

L&T Realty's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA29
Total units across these projects4,949
Completed without extending the possession date11
Completed after an extension3
Lapsed3
Under construction12
Possession date extended on the builder's application8
Typical time from launch to 100% structure4 years 5 months
MahaRERA complaints (filed by or against the builder), all L&T Realty projects114 (16 of 29 projects)

See all L&T Realty projects →