Aurus, Ghatkopar East
by M/s. B CHOPDA REALTORS · Ghatkopar East, Mumbai 400077 · Map
- Launched
- Apr 20242 yrs 11 mths promised
- Possession (MahaRERA)
- Mar 2027Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 10 of 2050% · 31 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale10 booked out of 20 units
Rehab31 units for existing members
Total 51 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 3
- 2 BHK
- 23
- 3 BHK
- 25
- Total units
- 51
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 20
- Rehab units
- 31
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 92% | 0% | 0% | 10 | |
| 92% | 0% | 0% | 10 | |
| 92% | 0% | 0% | 5 | |
| 75% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400077
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 11 mths | 4 yrs 4 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Mar 2027 | Sep 2028 |
| Concrete structure (RCC) | 0% | 100% |
| Units booked (free sale) | 50% | 59% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Rdk Rivanta, Ghatkopar East
- Ruparel Pristine, Ghatkopar East
- Vraj Emerald 60-Saikrupa, Ghatkopar East
- Silver Stellar, Ghatkopar East
- Om Neeldhara, Ghatkopar East
- KABRA EMBRAZE - Redevelopment of Shree Sahawas CHSL, Ghatkopar East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Rdk Rivanta | April 2024 | May 2029 | 100% | 12 units booked out of 34 units for sale |
| Ruparel Pristine | April 2024 | December 2026 | 100% | 60 units booked out of total 72 units |
| Vraj Emerald 60-Saikrupa | March 2024 | December 2029 | 66% | – |
| Silver Stellar | May 2024 | December 2028 | 100% | 26 units booked out of total 44 units |
| Om Neeldhara | May 2024 | June 2028 | 100% | 22 units booked out of 27 units for sale |
| KABRA EMBRAZE - Redevelopment of Shree Sahawas CHSL | May 2024 | December 2027 | 100% | 18 units booked out of 53 units for sale |
About this project
Aurus by M/s. B CHOPDA REALTORS is a 51-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in April 2024 with possession due in March 2027. 10 units booked out of 20 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Aurus is a BMC-sanctioned project by M/s. B CHOPDA REALTORS in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800055507. It was launched in April 2024. It has 51 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 51 units, 20 are for sale and 31 are rehab units for existing members.
Its registered possession date is March 2027, unchanged since launch. Construction: excavation 92% complete, structure (RCC) not started, final finishes not started.
10 units booked out of 20 units for sale (50%).