Vraj Emerald 60-Saikrupa, Ghatkopar East
by Vraj Kamman Developers · Ghatkopar East, Mumbai 400077 · Map
- Launched
- Mar 20245 yrs 9 mths promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 66%Mid-construction
- Booked
- –
- Buildings
- 20.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 4
- 1 BHK
- 28
- 2 BHK
- 23
- Other units
- 6
- Total units
- 61
- Buildings
- 2
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 66% | 0% | – | |
| 100% | 66% | 0% | – | |
| 100% | 66% | 0% | – | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400077
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 9 mths | 4 yrs |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2029 | Mar 2028 |
| Concrete structure (RCC) | 66% | 100% |
| Units booked | – | 65% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Rdk Rivanta, Ghatkopar East
- Aurus, Ghatkopar East
- Ruparel Pristine, Ghatkopar East
- Om Neeldhara, Ghatkopar East
- Silver Stellar, Ghatkopar East
- Park View, Ghatkopar East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Rdk Rivanta | April 2024 | May 2029 | 100% | 12 units booked out of 34 units for sale |
| Aurus | April 2024 | March 2027 | 0% | 10 units booked out of 20 units for sale |
| Ruparel Pristine | April 2024 | December 2026 | 100% | 60 units booked out of total 72 units |
| Om Neeldhara | May 2024 | June 2028 | 100% | 22 units booked out of 27 units for sale |
| Silver Stellar | May 2024 | December 2028 | 100% | 26 units booked out of total 44 units |
| Park View | January 2024 | December 2027 | 88% | 15 units booked out of 21 units for sale |
About this project
Vraj Emerald 60-Saikrupa by Vraj Kamman Developers is a 61-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in March 2024 with possession due in December 2029. The concrete structure (RCC) is 66% complete.
Read full summary
Vraj Emerald 60-Saikrupa is a BMC-sanctioned project by Vraj Kamman Developers in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800055177. It was launched in March 2024. It has 61 units in 2 buildings: 55 homes (1 RK, 1 BHK and 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 66% complete, final finishes not started.