Shraddha Park City, Borivali East

by Shraddha Prime Projects Limited · Borivali East, Mumbai 400066 · Map

Launched
Apr 20245 yrs 8 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
563 of 99956% · 334 rehab units
Buildings
73.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale563 booked out of 999 units

Rehab334 units for existing members

Total 1,333 units. Rehab units are not for sale.

Project facts

1 BHK
446
2 BHK
751
3 BHK
1
Other units
135
Total units
1,333
Buildings
7
Land
3.2 acres
Phases
1
MahaRERA complaints
1
Free-sale units
999
Rehab units
334

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%563
0%0%0%365
0%0%0%46

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Shraddha Park City by Shraddha Prime Projects Limited is a 1,333-unit SRA-sanctioned project in Borivali East, Mumbai 400066, launched in April 2024 with possession due in December 2029. 563 units booked out of 999 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Shraddha Park City is an SRA-sanctioned project by Shraddha Prime Projects Limited in Borivali East, Mumbai 400066, registered with MahaRERA as P51800055750. It was launched in April 2024. It has 1,333 units in 7 buildings: 1,198 homes (1, 2 and 3 BHK) and 135 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 1,333 units, 999 are for sale and 334 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

563 units booked out of 999 units for sale (56%). Since the December 2025 update, 198 more units have been booked.

Shraddha's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA53
Total units across these projects9,707
Completed without extending the possession date16
Completed after an extension4
Lapsed5
Under construction28
Possession date extended on the builder's application18
Typical time from launch to 100% structure4 years
MahaRERA complaints (filed by or against the builder), all Shraddha projects14 (11 of 53 projects)