Shree Ganesh Chsl, Dahisar

by Shri Ranchhodji Real Developrs · Dahisar, Mumbai 400068 · Map

Launched
Apr 20241 yr 11 mths originally promised
Possession (MahaRERA)
Jul 2027Extended by 1 yr 4 mths
Concrete structure
100%Nearing possession
Booked (free sale)
0 of 80% · 10 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 8 units

Rehab10 units for existing members

Total 18 units. Rehab units are not for sale.

Project facts

1 BHK
10
2 BHK
8
Total units
18
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
8
Rehab units
10

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%0
100%0%0%0
100%0%0%0
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400068

Projects with up to 40 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400068
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 11 mths3 yrs 6 mths
Possession date extendedBy 1 yr 4 mths0 of 3
Possession date (MahaRERA)Jul 2027Dec 2027
Concrete structure (RCC)100%70%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Shree Ganesh Chsl by Shri Ranchhodji Real Developrs is an 18-unit BMC-sanctioned project in Dahisar, Mumbai 400068, launched in April 2024 with possession due in July 2027. 0 units booked out of 8 units for sale. The concrete structure (RCC) is complete.

Read full summary

Shree Ganesh Chsl is a BMC-sanctioned project by Shri Ranchhodji Real Developrs in Dahisar, Mumbai 400068, registered with MahaRERA as P51800055912. It was launched in April 2024. It has 18 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 18 units, 8 are for sale and 10 are rehab units for existing members.

Its registered possession date is July 2027, extended by 1 year 4 months from the original March 2026. Construction: excavation complete, structure (RCC) complete, final finishes not started.

0 units booked out of 8 units for sale (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 100% and the possession date has moved from March 2026 to July 2027.