Rajaram, Dahisar
by Ummang Realtors · Dahisar, Mumbai 400068 · Map
- Launched
- May 20243 yrs 7 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 70%Mid-construction
- Booked (free sale)
- 2 of 2100% · 32 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale2 booked out of 2 units
Rehab32 units for existing members
Total 34 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 3
- 2 BHK
- 23
- 3 BHK
- 1
- Other units
- 7
- Total units
- 34
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 2
- Rehab units
- 32
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 70% | 0% | 2 | |
| 100% | 70% | 0% | 2 | |
| 100% | 65% | 0% | 2 | |
| 100% | 65% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400068
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 7 mths | 3 yrs 4 mths |
| Possession date extended | No | 1 of 5 |
| Possession date (MahaRERA) | Dec 2027 | Oct 2027 |
| Concrete structure (RCC) | 70% | 100% |
| Units booked (free sale) | 100% | 56% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Hum Durga, Dahisar
- Nandanvan Mohan CHSL, Dahisar
- Shree Ganesh Chsl, Dahisar
- Krishnaraj Buildcon New Suryadarshan Co Op Hsg. Soc, Dahisar
- Muktangan Residency, Dahisar
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Hum Durga | May 2024 | December 2026 | 100% | – |
| Nandanvan Mohan CHSL | June 2024 | December 2027 | 11% | 29 units booked out of 36 units for sale |
| Shree Ganesh Chsl | April 2024 | July 2027 | 100% | 0 units booked out of 8 units for sale |
| Krishnaraj Buildcon New Suryadarshan Co Op Hsg. Soc | August 2024 | December 2027 | 30% | 8 units booked out of 20 units for sale |
| Muktangan Residency | January 2024 | October 2027 | 100% | 24 units booked out of 33 units for sale |
About this project
Rajaram by Ummang Realtors is a 34-unit BMC-sanctioned project in Dahisar, Mumbai 400068, launched in May 2024 with possession due in December 2027. 2 units booked out of 2 units for sale. The concrete structure (RCC) is 70% complete.
Read full summary
Rajaram is a BMC-sanctioned project by Ummang Realtors in Dahisar, Mumbai 400068, registered with MahaRERA as P51800056207. It was launched in May 2024. It has 34 units in 1 building: 27 homes (1, 2 and 3 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 34 units, 2 are for sale and 32 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 70% complete, final finishes not started.
2 units booked out of 2 units for sale (100%).