Skip to main content

Skyline103, Borivali West

by Panchnaad Developers · Borivali West, Mumbai 400103 · Map

Launched
May 20242 yrs 10 mths promised
Possession (MahaRERA)
Mar 2027Not extended
Concrete structure
47%Mid-construction
Booked (free sale)
3 of 1718% · 13 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale3 booked out of 17 units

Rehab13 units for existing members

Total 30 units. Rehab units are not for sale.

Project facts

1 BHK
8
2 BHK
20
3 BHK
2
Total units
30
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
17
Rehab units
13

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)47%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 47%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 47%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%47%0%3
100%0%0%3
100%0%0%–
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400103

Projects with 10–60 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400103
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 10 mths2 yrs 11 mths
Possession date extendedNo1 of 3
Possession date (MahaRERA)Mar 2027Dec 2027
Concrete structure (RCC)47%14%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Skyline103 by Panchnaad Developers is a 30-unit BMC-sanctioned project in Borivali West, Mumbai 400103, launched in May 2024 with possession due in March 2027. 3 units booked out of 17 units for sale. The concrete structure (RCC) is 47% complete.

Read full summary

Skyline103 is a BMC-sanctioned project by Panchnaad Developers in Borivali West, Mumbai 400103, registered with MahaRERA as P51800056127. It was launched in May 2024. It has 30 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 30 units, 17 are for sale and 13 are rehab units for existing members.

Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 47% complete, final finishes not started.

3 units booked out of 17 units for sale (18%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 47%.