Rishabraj Astral, Borivali West
by Rishabraj Estate Developers Pvt Ltd · Borivali West, Mumbai 400103 · Map
- Launched
- Oct 20244 yrs 10 mths promised
- Possession (MahaRERA)
- Aug 2029Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 8 of 8100% · 20 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale8 booked out of 8 units
Rehab20 units for existing members
Total 28 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 3
- 2 BHK
- 11
- 3 BHK
- 2
- Other units
- 12
- Total units
- 28
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 8
- Rehab units
- 20
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 60% | 8 | |
| 100% | 100% | 0% | 8 | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400103
Projects with up to 40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 10 mths | 2 yrs 10 mths |
| Possession date extended | No | 1 of 4 |
| Possession date (MahaRERA) | Aug 2029 | Sep 2027 |
| Concrete structure (RCC) | 100% | 7% |
| Units booked (free sale) | 100% | 43% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Hariko Brahma, Borivali West
- Questend Co Op Housing Society Ltd, Borivali West
- Lourdes Chsl, Borivali West
- Skyline103, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Hariko Brahma | January 2025 | December 2029 | 0% | 10 units booked out of total 23 units |
| Questend Co Op Housing Society Ltd | January 2025 | December 2027 | 0% | – |
| Lourdes Chsl | May 2024 | June 2027 | 14% | 15 units booked out of 15 units for sale |
| Skyline103 | May 2024 | March 2027 | 47% | 3 units booked out of 17 units for sale |
About this project
Rishabraj Astral by Rishabraj Estate Developers Pvt Ltd is a 28-unit BMC-sanctioned project in Borivali West, Mumbai 400103, launched in October 2024 with possession due in August 2029. 8 units booked out of 8 units for sale. The concrete structure (RCC) is complete.
Read full summary
Rishabraj Astral is a BMC-sanctioned project by Rishabraj Estate Developers Pvt Ltd in Borivali West, Mumbai 400103, registered with MahaRERA as P51800077784. It was launched in October 2024. It has 28 units in 1 building: 16 homes (1, 2 and 3 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 28 units, 8 are for sale and 20 are rehab units for existing members.
Its registered possession date is August 2029, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 60% complete.
8 units booked out of 8 units for sale (100%).
Rishabraj's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 43 |
|---|---|
| Total units across these projects | 1,514 |
| Completed without extending the possession date | 22 |
| Completed after an extension | 3 |
| Lapsed | 3 |
| Under construction | 15 |
| Possession date extended on the builder's application | 4 |
| Typical time from launch to 100% structure | 2 years 9 months |
| MahaRERA complaints (filed by or against the builder), all Rishabraj projects | 33 (4 of 43 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.