Skip to main content

Rishabraj Astral, Borivali West

by Rishabraj Estate Developers Pvt Ltd · Borivali West, Mumbai 400103 · Map

Launched
Oct 20244 yrs 10 mths promised
Possession (MahaRERA)
Aug 2029Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
8 of 8100% · 20 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale8 booked out of 8 units

Rehab20 units for existing members

Total 28 units. Rehab units are not for sale.

Project facts

1 BHK
3
2 BHK
11
3 BHK
2
Other units
12
Total units
28
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
8
Rehab units
20

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services60%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 60%Excavation 100%Concrete structure (RCC) 100%Final finishes 60%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%60%8
100%100%0%8
0%0%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400103

Projects with up to 40 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400103
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 10 mths2 yrs 10 mths
Possession date extendedNo1 of 4
Possession date (MahaRERA)Aug 2029Sep 2027
Concrete structure (RCC)100%7%
Units booked (free sale)100%43%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Rishabraj Astral by Rishabraj Estate Developers Pvt Ltd is a 28-unit BMC-sanctioned project in Borivali West, Mumbai 400103, launched in October 2024 with possession due in August 2029. 8 units booked out of 8 units for sale. The concrete structure (RCC) is complete.

Read full summary

Rishabraj Astral is a BMC-sanctioned project by Rishabraj Estate Developers Pvt Ltd in Borivali West, Mumbai 400103, registered with MahaRERA as P51800077784. It was launched in October 2024. It has 28 units in 1 building: 16 homes (1, 2 and 3 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 28 units, 8 are for sale and 20 are rehab units for existing members.

Its registered possession date is August 2029, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 60% complete.

8 units booked out of 8 units for sale (100%).

Rishabraj's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA43
Total units across these projects1,514
Completed without extending the possession date22
Completed after an extension3
Lapsed3
Under construction15
Possession date extended on the builder's application4
Typical time from launch to 100% structure2 years 9 months
MahaRERA complaints (filed by or against the builder), all Rishabraj projects33 (4 of 43 projects)

See all Rishabraj projects →