Artha, Khar West

by Aum Lifespaces · Khar West, Mumbai 400052 · Map

Launched
May 20243 yrs 7 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
12 of 1771% · 32 rehab units
Buildings
20.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale12 booked out of 17 units

Rehab32 units for existing members

Total 49 units. Rehab units are not for sale.

Project facts

2 BHK
12
3 BHK
28
4 BHK
7
Other units
2
Total units
49
Buildings
2
Land
0.6 acres
Phases
1
MahaRERA complaints
0
Free-sale units
17
Rehab units
32

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Oct 2026Dec 2024: Excavation 95%Dec 2025: Excavation 95%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 91%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Oct 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 100%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%50%12
95%91%0%11
95%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400052

Projects with 20–100 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400052
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 7 mths4 yrs
Possession date extendedNo0 of 4
Possession date (MahaRERA)Dec 2027Jun 2028
Concrete structure (RCC)100%75%
Units booked (free sale)71%69%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Artha by Aum Lifespaces is a 49-unit BMC-sanctioned project in Khar West, Mumbai 400052, launched in May 2024 with possession due in December 2027. 12 units booked out of 17 units for sale. The concrete structure (RCC) is complete.

Read full summary

Artha is a BMC-sanctioned project by Aum Lifespaces in Khar West, Mumbai 400052, registered with MahaRERA as P51800056140. It was launched in May 2024. It has 49 units in 2 buildings: 47 homes (2, 3 and 4 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 49 units, 17 are for sale and 32 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.

12 units booked out of 17 units for sale (71%). Since the December 2025 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 91% to 100%.