Edge, Khar West

by Join Trak Infra Private Limited · Khar West, Mumbai 400052 · Map

Launched
Jun 20244 yrs 6 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
50%Mid-construction
Booked (free sale)
2 of 540% · 32 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale2 booked out of 5 units

Rehab32 units for existing members

Total 37 units. Rehab units are not for sale.

Project facts

2 BHK
37
Total units
37
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
5
Rehab units
32

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)50%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 40%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 15%Oct 2026: Concrete structure (RCC) 50%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 50%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%50%0%2
100%15%0%2
100%0%0%1
40%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400052

Projects with 10–80 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400052
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 6 mths3 yrs 4 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2028Dec 2027
Concrete structure (RCC)50%100%
Units booked (free sale)40%71%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Edge by Join Trak Infra Private Limited is a 37-unit BMC-sanctioned project in Khar West, Mumbai 400052, launched in June 2024 with possession due in December 2028. 2 units booked out of 5 units for sale. The concrete structure (RCC) is 50% complete.

Read full summary

Edge is a BMC-sanctioned project by Join Trak Infra Private Limited in Khar West, Mumbai 400052, registered with MahaRERA as P51800066562. It was launched in June 2024. It has 37 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 37 units, 5 are for sale and 32 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 50% complete, final finishes not started.

2 units booked out of 5 units for sale (40%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 15% to 50%.