by Blue Ocean Realty · Dahisar, Mumbai 400068 · Map

Launched
May 20243 yrs 7 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
89%Mid-construction
Booked (free sale)
102 of 12383% · 44 rehab units
Buildings
20.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale102 booked out of 123 units

Rehab44 units for existing members

Land-owner share8 units, not for sale

Total 175 units. Rehab and land-owner units are not for sale.

Project facts

1 BHK
123
2 BHK
50
Other units
2
Total units
175
Buildings
2
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
123
Rehab units
44
Land-owner share (not for sale)
8

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)89%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 70%Dec 2025: Excavation 70%Jul 2026: Excavation 70%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 89%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 89%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%89%0%102
70%0%0%46
70%0%0%46
70%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400068

Projects with 80–350 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400068
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 7 mths4 yrs 2 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2027Sep 2028
Concrete structure (RCC)89%62%
Units booked (free sale)83%42%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Ozone Residency by Blue Ocean Realty is a 175-unit BMC-sanctioned project in Dahisar, Mumbai 400068, launched in May 2024 with possession due in December 2027. 102 units booked out of 123 units for sale. The concrete structure (RCC) is 89% complete.

Read full summary

Ozone Residency is a BMC-sanctioned project by Blue Ocean Realty in Dahisar, Mumbai 400068, registered with MahaRERA as P51800056206. It was launched in May 2024. It has 175 units in 2 buildings: 173 homes (1 and 2 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 175 units, 123 are for sale, 44 are rehab units for existing members and 8 are the land-owner's share, not for sale.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 89% complete, final finishes not started.

102 units booked out of 123 units for sale (83%). Since the July 2026 update, 56 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 89%.