Skip to main content

Modirealty Acacia, Dahisar

Ready to move

by Modirealty Developers Pvt Ltd · Dahisar, Mumbai 400068 · Map

Launched
May 20243 yrs 10 mths promised
Possession (MahaRERA)
Mar 2028Not extended
Concrete structure
100%Ready to move
Booked (free sale)
61 of 9664% · 39 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale61 booked out of 96 units

Rehab39 units for existing members

Total 135 units. Rehab units are not for sale.

Project facts

1 BHK
23
2 BHK
96
3 BHK
16
Total units
135
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
96
Rehab units
39

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 5%Dec 2025: Concrete structure (RCC) 65%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 50%Oct 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%61
100%100%50%59
100%65%0%32
100%5%0%19

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400068

Projects with 60–300 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400068
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 10 mths4 yrs 2 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Mar 2028Jun 2028
Concrete structure (RCC)100%76%
Units booked (free sale)64%50%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Modirealty Acacia by Modirealty Developers Pvt Ltd is a 135-unit MHADA-sanctioned project in Dahisar, Mumbai 400068, launched in May 2024 with possession due in March 2028. 61 units booked out of 96 units for sale. The concrete structure (RCC) is complete.

Read full summary

Modirealty Acacia is a MHADA-sanctioned project by Modirealty Developers Pvt Ltd in Dahisar, Mumbai 400068, registered with MahaRERA as P51800056150. It was launched in May 2024. It has 135 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 135 units, 96 are for sale and 39 are rehab units for existing members.

Its registered possession date is March 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

61 units booked out of 96 units for sale (64%). Since the July 2026 update, 2 more units have been booked.