Bhandup Siddhivinayak CHS Ltd, Bhandup East
by Shraddha Landmark Private Limited · Bhandup East, Mumbai 400042 · Map
- Launched
- May 20244 yrs 1 mth promised
- Possession (MahaRERA)
- Jun 2028Not extended
- Concrete structure
- 87%Mid-construction
- Booked (free sale)
- 12 of 3238% · 20 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale12 booked out of 32 units
Rehab20 units for existing members
Total 52 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 13
- 2 BHK
- 38
- Other units
- 1
- Total units
- 52
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 32
- Rehab units
- 20
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 87% | 0% | 12 | |
| 100% | 22% | 0% | – | |
| 100% | 22% | 0% | – | |
| 100% | 4% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Bhandup Siddhivinayak CHS Ltd by Shraddha Landmark Private Limited is a 52-unit SRA-sanctioned project in Bhandup East, Mumbai 400042, launched in May 2024 with possession due in June 2028. 12 units booked out of 32 units for sale. The concrete structure (RCC) is 87% complete.
Read full summary
Bhandup Siddhivinayak CHS Ltd is an SRA-sanctioned project by Shraddha Landmark Private Limited in Bhandup East, Mumbai 400042, registered with MahaRERA as P51800056282. It was launched in May 2024. It has 52 units in 1 building: 51 homes (1 and 2 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 52 units, 32 are for sale and 20 are rehab units for existing members.
Its registered possession date is June 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 87% complete, final finishes not started.
12 units booked out of 32 units for sale (38%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 22% to 87%.
Shraddha's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 53 |
|---|---|
| Total units across these projects | 9,707 |
| Completed without extending the possession date | 16 |
| Completed after an extension | 4 |
| Lapsed | 5 |
| Under construction | 28 |
| Possession date extended on the builder's application | 18 |
| Typical time from launch to 100% structure | 4 years |
| MahaRERA complaints (filed by or against the builder), all Shraddha projects | 14 (11 of 53 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.