Sky Heights C-D, Andheri West
by R S Estate Developers Pvt Ltd · Andheri West, Mumbai 400053 · Map
- Launched
- May 20244 yrs 1 mth promised
- Possession (MahaRERA)
- Jun 2028Not extended
- Concrete structure
- 90%Mid-construction
- Booked
- 13 of 5623% · 9 in Jul 2026
- Buildings
- 10.5 acres
- MahaRERA complaints
- 6Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 3
- 5+ BHK
- 51
- Other units
- 2
- Total units
- 56
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 6
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 90% | 0% | 13 | |
| 100% | 69% | 0% | 9 | |
| 100% | 52% | 0% | 9 | |
| 100% | 13% | 0% | 4 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400053
Projects with 20–150 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 1 mth | 5 yrs 3 mths |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Jun 2028 | Dec 2028 |
| Concrete structure (RCC) | 90% | 95% |
| MahaRERA complaints (filed by or against the builder) | 6 | 0 |
The 3 projects
- Westwood, Andheri West
- Gurukrupa Dhyanam, Andheri West
- Lashkaria Indrasukh, Andheri West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Westwood | May 2024 | December 2029 | 0% | – |
| Gurukrupa Dhyanam | April 2024 | March 2027 | 100% | 82 units booked out of total 111 units |
| Lashkaria Indrasukh | September 2023 | December 2028 | 95% | 47 units booked out of 64 units for sale |
About this project
Sky Heights C-D by R S Estate Developers Pvt Ltd is a 56-unit BMC-sanctioned project in Andheri West, Mumbai 400053, launched in May 2024 with possession due in June 2028. 13 units booked out of total 56 units. The concrete structure (RCC) is 90% complete.
Read full summary
Sky Heights C-D is a BMC-sanctioned project by R S Estate Developers Pvt Ltd in Andheri West, Mumbai 400053, registered with MahaRERA as P51800056425. It was launched in May 2024. It has 56 units in 1 building: 54 homes (2 and 5+ BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is June 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 90% complete, final finishes not started.
13 units booked out of total 56 units (23%). Since the July 2026 update, 4 more units have been booked and the reported concrete structure (RCC) has gone from 69% to 90%.