Lashkaria Indrasukh, Andheri West
by Lashkaria Housing & infrastructure Limited · Andheri West, Mumbai 400053 · Map
- Launched
- Sep 20235 yrs 3 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 95%Mid-construction
- Booked (free sale)
- 47 of 6473% · 47 rehab units
- Buildings
- 30.8 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale47 booked out of 64 units
Rehab47 units for existing members
Total 111 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 39
- 3 BHK
- 54
- 4 BHK
- 1
- Other units
- 17
- Total units
- 111
- Buildings
- 3
- Land
- 0.8 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 64
- Rehab units
- 47
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 95% | 20% | 47 | |
| 100% | 95% | 20% | 45 | |
| 100% | 40% | 0% | 27 | |
| 100% | 40% | 0% | 18 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400053
Projects with 40–200 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 3 mths | 3 yrs 10 mths |
| Possession date extended | No | 1 of 4 |
| Possession date (MahaRERA) | Dec 2028 | Nov 2027 |
| Concrete structure (RCC) | 95% | 45% |
| Units booked (free sale) | 73% | 47% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Tru Gardenia, Andheri West
- Mantri Our Home, Andheri West
- Gurukrupa Dhyanam, Andheri West
- Sky Heights C-D, Andheri West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Tru Gardenia | September 2023 | April 2029 | 0% | 15 units booked out of 70 units for sale |
| Mantri Our Home | June 2023 | March 2027 | 0% | 38 units booked out of 54 units for sale |
| Gurukrupa Dhyanam | April 2024 | March 2027 | 100% | 82 units booked out of total 111 units |
| Sky Heights C-D | May 2024 | June 2028 | 90% | 13 units booked out of total 56 units |
About this project
Lashkaria Indrasukh by Lashkaria Housing & infrastructure Limited is a 111-unit BMC-sanctioned project in Andheri West, Mumbai 400053, launched in September 2023 with possession due in December 2028. 47 units booked out of 64 units for sale. The concrete structure (RCC) is 95% complete.
Read full summary
Lashkaria Indrasukh is a BMC-sanctioned project by Lashkaria Housing & infrastructure Limited in Andheri West, Mumbai 400053, registered with MahaRERA as P51800052471. It was launched in September 2023. It has 111 units in 3 buildings: 94 homes (2, 3 and 4 BHK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 111 units, 64 are for sale and 47 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 95% complete, final finishes 20% complete.
47 units booked out of 64 units for sale (73%). Since the July 2026 update, 2 more units have been booked.