Skip to main content

Woods Tower 9, Kandivali East

by Lodha Developers Limited · Kandivali East, Mumbai 400101 · Map

Launched
Jun 20244 yrs 6 mths originally promised
Possession (MahaRERA)
Dec 2029Extended by 1 yr
Concrete structure
0%Early stage
Booked
14 of 3244% · 12 in Jul 2026
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

4 BHK
28
5+ BHK
2
Other units
2
Total units
32
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 15%Jul 2026: Excavation 30%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%14
30%0%0%12
15%0%0%9
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Woods Tower 9 by Lodha Developers Limited is a 32-unit BMC-sanctioned project in Kandivali East, Mumbai 400101, launched in June 2024 with possession due in December 2029. 14 units booked out of total 32 units. Work on the concrete structure (RCC) has not started.

Read full summary

Woods Tower 9 is a BMC-sanctioned project by Lodha Developers Limited in Kandivali East, Mumbai 400101, registered with MahaRERA as P51800056457. It was launched in June 2024. It has 32 units in 1 building: 30 homes (4 and 5+ BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, extended by 1 year from the original December 2028. Construction: excavation complete, structure (RCC) not started, final finishes not started.

14 units booked out of total 32 units (44%). Since the July 2026 update, 2 more units have been booked.

Lodha's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA85
Total units across these projects15,101
Completed without extending the possession date31
Completed after an extension13
Lapsed0
Under construction41
Possession date extended on the builder's application34
Typical time from launch to 100% structure5 years 10 months
MahaRERA complaints (filed by or against the builder), all Lodha projects242 (38 of 85 projects)

See all Lodha projects →