Skip to main content

Aneesh Apartment Co.op. Housing Soc. Ltd, Andheri West

Ready to move

by Banaji Silverline Developers LLP · Andheri West, Mumbai 400058 · Map

Launched
Jun 20243 yrs 6 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
100%Ready to move
Booked (free sale)
5 of 1050% · 13 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale5 booked out of 10 units

Rehab13 units for existing members

Total 23 units. Rehab units are not for sale.

Project facts

1 RK
1
2 BHK
8
3 BHK
11
4 BHK
3
Total units
23
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
10
Rehab units
13

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 40%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 30%Jul 2026: Final finishes 80%Oct 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%5
100%100%80%10
100%100%30%10
100%40%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400058

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400058
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 6 mths3 yrs 8 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Dec 2027Dec 2027
Concrete structure (RCC)100%90%
Units booked (free sale)50%5%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Aneesh Apartment Co.op. Housing Soc. Ltd by Banaji Silverline Developers LLP is a 23-unit BMC-sanctioned project in Andheri West, Mumbai 400058, launched in June 2024 with possession due in December 2027. 5 units booked out of 10 units for sale. The concrete structure (RCC) is complete.

Read full summary

Aneesh Apartment Co.op. Housing Soc. Ltd is a BMC-sanctioned project by Banaji Silverline Developers LLP in Andheri West, Mumbai 400058, registered with MahaRERA as P51800056463. It was launched in June 2024. It has 23 units in 1 building, with 1 RK, 2 BHK, 3 BHK and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 23 units, 10 are for sale and 13 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

5 units booked out of 10 units for sale (50%).