Delta Meadows, Andheri West
by Delta Synergy LLP · Andheri West, Mumbai 400058 · Map
- Launched
- Dec 20242 yrs 6 mths promised
- Possession (MahaRERA)
- Jun 2027Not extended
- Concrete structure
- 44%Mid-construction
- Booked (free sale)
- 1 of 119% · 32 rehab units
- Buildings
- 20.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale1 booked out of 11 units
Rehab32 units for existing members
Total 43 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 19
- 2 BHK
- 9
- 3 BHK
- 4
- Other units
- 11
- Total units
- 43
- Buildings
- 2
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 11
- Rehab units
- 32
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 44% | 0% | 1 | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400058
Projects with 10–70 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 6 mths | 2 yrs 8 mths |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | Jun 2027 | Dec 2027 |
| Concrete structure (RCC) | 44% | 60% |
| Units booked (free sale) | 9% | 27% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Boston Harbor, Andheri West
- Sun Sumit Yashodhan, Andheri West
- Parshwa Darshan Phase 1, Andheri West
- Aneesh Apartment Co.op. Housing Soc. Ltd, Andheri West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Boston Harbor | February 2025 | September 2027 | 0% | 11 units booked out of 50 units for sale |
| Sun Sumit Yashodhan | March 2025 | December 2027 | 84% | 4 units booked out of 22 units for sale |
| Parshwa Darshan Phase 1 | April 2025 | December 2027 | 35% | 8 units booked out of 25 units for sale |
| Aneesh Apartment Co.op. Housing Soc. Ltd | June 2024 | December 2027 | 100% | 5 units booked out of 10 units for sale |
About this project
Delta Meadows by Delta Synergy LLP is a 43-unit BMC-sanctioned project in Andheri West, Mumbai 400058, launched in December 2024 with possession due in June 2027. 1 unit booked out of 11 units for sale. The concrete structure (RCC) is 44% complete.
Read full summary
Delta Meadows is a BMC-sanctioned project by Delta Synergy LLP in Andheri West, Mumbai 400058, registered with MahaRERA as P51800078499. It was launched in December 2024. It has 43 units in 2 buildings: 32 homes (1, 2 and 3 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 43 units, 11 are for sale and 32 are rehab units for existing members.
Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 44% complete, final finishes not started.
1 unit booked out of 11 units for sale (9%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 44%.