Priyam Residency, Malad West
by Priyam Projects (I) Private Limited · Malad West, Mumbai 400064 · Map
- Launched
- Jun 20242 yrs originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 1 yr 6 mths
- Concrete structure
- 78%Mid-construction
- Booked
- 81 of 16150% · 51 in Jul 2026
- Buildings
- 30.5 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 151
- 2 BHK
- 8
- Other units
- 2
- Total units
- 161
- Buildings
- 3
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Reserved units
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 78% | 15% | 81 | |
| 100% | 51% | 15% | 51 | |
| 100% | 53% | 15% | 13 | |
| 100% | 0% | 0% | 2 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400064
Projects with 70–350 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs | 3 yrs 5 mths |
| Possession date extended | By 1 yr 6 mths | 0 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Dec 2027 |
| Concrete structure (RCC) | 78% | 63% |
| Units booked | 50% | 42% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 6 projects
- Redevelopment Of Kaveri Chsl, Malad West
- Shreeji Bliss, Malad West
- Rashmi Signature, Malad West
- Redevelopment Of Glendon Chsl, Sheldon Chsl, Orlem Luciana Chsl, Malad West
- Auris Serenity Tower 4 Residential, Malad West
- Sharanya, Malad West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Redevelopment Of Kaveri Chsl | July 2024 | March 2028 | 66% | 37 units booked out of 61 units for sale |
| Shreeji Bliss | July 2024 | January 2028 | 31% | 37 units booked out of 90 units for sale |
| Rashmi Signature | July 2024 | August 2027 | 92% | 39 units booked out of 92 units for sale |
| Redevelopment Of Glendon Chsl, Sheldon Chsl, Orlem Luciana Chsl | July 2024 | November 2027 | 60% | 40 units booked out of 66 units for sale |
| Auris Serenity Tower 4 Residential | April 2024 | March 2030 | 0% | 9 units booked out of total 123 units |
| Sharanya | April 2024 | December 2026 | 100% | 24 units booked out of 87 units for sale |
About this project
Priyam Residency by Priyam Projects (I) Private Limited is a 161-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in June 2024 with possession due in December 2027. 81 units booked out of total 161 units. The concrete structure (RCC) is 78% complete.
Read full summary
Priyam Residency is a BMC-sanctioned project by Priyam Projects (I) Private Limited in Malad West, Mumbai 400064, registered with MahaRERA as P51800066519. It was launched in June 2024. It has 161 units in 3 buildings: 159 homes (1 and 2 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, extended by 1 year 6 months from the original June 2026. Construction: excavation complete, structure (RCC) 78% complete, final finishes 15% complete.
81 units booked out of total 161 units (50%). Since the July 2026 update, 30 more units have been booked and the reported concrete structure (RCC) has gone from 51% to 78%.