Skip to main content

Rashmi Signature, Malad West

by Modi's Navnirman Limited · Malad West, Mumbai 400064 · Map

Launched
Jul 20243 yrs 1 mth promised
Possession (MahaRERA)
Aug 2027Not extended
Concrete structure
92%Mid-construction
Booked (free sale)
39 of 9242% · 118 rehab units
Buildings
31.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale39 booked out of 92 units

Rehab118 units for existing members

Total 210 units. Rehab units are not for sale.

Project facts

2 BHK
141
3 BHK
69
Total units
210
Buildings
3
Land
1.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
92
Rehab units
118

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)92%
Finishes, lifts and services60%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 52%Jul 2026: Concrete structure (RCC) 86%Oct 2026: Concrete structure (RCC) 92%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 25%Oct 2026: Final finishes 60%Excavation 100%Concrete structure (RCC) 92%Final finishes 60%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%92%60%39
100%86%25%15
100%52%0%7
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400064

Projects with 100–450 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400064
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 1 mth3 yrs 7 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Aug 2027Feb 2028
Concrete structure (RCC)92%63%
Units booked (free sale)42%61%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Rashmi Signature by Modi's Navnirman Limited is a 210-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in July 2024 with possession due in August 2027. 39 units booked out of 92 units for sale. The concrete structure (RCC) is 92% complete.

Read full summary

Rashmi Signature is a BMC-sanctioned project by Modi's Navnirman Limited in Malad West, Mumbai 400064, registered with MahaRERA as P51800077248. It was launched in July 2024. It has 210 units in 3 buildings, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 210 units, 92 are for sale and 118 are rehab units for existing members.

Its registered possession date is August 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 92% complete, final finishes 60% complete.

39 units booked out of 92 units for sale (42%). Since the July 2026 update, 24 more units have been booked and the reported concrete structure (RCC) has gone from 86% to 92%.