Hari Om, Chembur
by Majestic Royale Developers · Chembur, Mumbai 400071 · Map
- Launched
- Jun 20243 yrs promised
- Possession (MahaRERA)
- Jun 2027Not extended
- Concrete structure
- 80%Mid-construction
- Booked (free sale)
- 11 of 3135% · 11 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale11 booked out of 31 units
Rehab11 units for existing members
Total 42 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 7
- 2 BHK
- 25
- 3 BHK
- 10
- Total units
- 42
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 31
- Rehab units
- 11
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 80% | 0% | 11 | |
| 100% | 67% | 0% | 5 | |
| 100% | 50% | 0% | 4 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400071
Projects with 20–90 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs | 2 yrs 8 mths |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Jun 2027 | Dec 2026 |
| Concrete structure (RCC) | 80% | 90% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Kranti Heights, Chembur
- Om Niwas, Chembur
- Vishva, Chembur
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Kranti Heights | June 2024 | September 2026 | 100% | 4 units booked out of 7 units for sale |
| Om Niwas | April 2024 | December 2026 | 90% | – |
| Vishva | August 2024 | May 2029 | 35% | 26 units booked out of 71 units for sale |
About this project
Hari Om by Majestic Royale Developers is a 42-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in June 2024 with possession due in June 2027. 11 units booked out of 31 units for sale. The concrete structure (RCC) is 80% complete.
Read full summary
Hari Om is a BMC-sanctioned project by Majestic Royale Developers in Chembur, Mumbai 400071, registered with MahaRERA as P51800066536. It was launched in June 2024. It has 42 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 42 units, 31 are for sale and 11 are rehab units for existing members.
Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 80% complete, final finishes not started.
11 units booked out of 31 units for sale (35%). Since the July 2026 update, 6 more units have been booked and the reported concrete structure (RCC) has gone from 67% to 80%.