Kranti Heights, Chembur

Ready to move

by Sidhivinayak Constructions · Chembur, Mumbai 400071 · Map

Launched
Jun 20242 yrs 3 mths promised
Possession (MahaRERA)
Sep 2026Not extended
Concrete structure
100%Ready to move
Booked (free sale)
4 of 757% · 14 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale4 booked out of 7 units

Rehab14 units for existing members

Total 21 units. Rehab units are not for sale.

Project facts

1 BHK
1
2 BHK
12
3 BHK
7
5+ BHK
1
Total units
21
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
7
Rehab units
14

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 95%Dec 2025: Excavation 95%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 10%Dec 2025: Concrete structure (RCC) 75%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 10%Oct 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%4
100%100%10%4
95%75%0%3
95%10%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400071

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 3 mths3 yrs
Possession date extendedNo0 of 5
Possession date (MahaRERA)Sep 2026Jun 2027
Concrete structure (RCC)100%90%
Units booked (free sale)57%50%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Kranti Heights by Sidhivinayak Constructions is a 21-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in June 2024 with possession due in September 2026. 4 units booked out of 7 units for sale. The concrete structure (RCC) is complete.

Read full summary

Kranti Heights is a BMC-sanctioned project by Sidhivinayak Constructions in Chembur, Mumbai 400071, registered with MahaRERA as P51800076833. It was launched in June 2024. It has 21 units in 1 building, with 1, 2, 3 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 21 units, 7 are for sale and 14 are rehab units for existing members.

Possession was due in September 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

4 units booked out of 7 units for sale (57%).