Rustomjee Ocean Vista, Versova
by Keyspace Realtors Private Limited · Versova, Mumbai 400061 · Map
- Launched
- Jun 20244 yrs 11 mths promised
- Possession (MahaRERA)
- May 2029Not extended
- Concrete structure
- 10%Mid-construction
- Booked (free sale)
- 20 of 3262% · 24 rehab units
- Buildings
- 10.6 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale20 booked out of 32 units
Rehab24 units for existing members
Total 56 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 4
- 2 BHK
- 16
- 3 BHK
- 8
- 4 BHK
- 23
- 5+ BHK
- 5
- Total units
- 56
- Buildings
- 1
- Land
- 0.6 acres
- Phases
- 1
- MahaRERA complaints
- 2
- Free-sale units
- 32
- Rehab units
- 24
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 10% | 0% | 20 | |
| 100% | 0% | 0% | 20 | |
| 7% | 0% | 0% | – | |
| 7% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Rustomjee Ocean Vista by Keyspace Realtors Private Limited (Rustomjee) is a 56-unit SRA-sanctioned project in Versova, Mumbai 400061, launched in June 2024 with possession due in May 2029. 20 units booked out of 32 units for sale. The concrete structure (RCC) is 10% complete.
Read full summary
Rustomjee Ocean Vista is an SRA-sanctioned project by Keyspace Realtors Private Limited in Versova, Mumbai 400061, registered with MahaRERA as P51800076673. It was launched in June 2024. It has 56 units in 1 building, with 1, 2, 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 56 units, 32 are for sale and 24 are rehab units for existing members.
Its registered possession date is May 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 10% complete, final finishes not started.
20 units booked out of 32 units for sale (62%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 10%.
Rustomjee's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 38 |
|---|---|
| Total units across these projects | 3,435 |
| Completed without extending the possession date | 15 |
| Completed after an extension | 2 |
| Lapsed | 5 |
| Under construction | 16 |
| Possession date extended on the builder's application | 8 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Rustomjee projects | 119 (11 of 38 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.