Rustomjee projects in Mumbai
MahaRERA projects by Rustomjee registered 2017–2026 in Mumbai.
| Projects registered with MahaRERA | 38 |
|---|---|
| Total units across these projects | 3,435 |
Full record
MahaRERA projects registered 2017–2026 in Mumbai
| Completed without extending the possession date | 15 |
|---|---|
| Completed after an extension | 2 |
| Lapsed | 5 |
| Under construction | 16 |
| Possession date extended on the builder's application | 8 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Rustomjee projects | 119 (11 of 38 projects) |
What these mean
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Where they build: Bandra East (6) · Khar West (4) · Bandra West (3) · Andheri West (2) · Borivali East (2) · Malad West (2) · Dadar East (2) · Andheri East (1) · Santacruz West (1) · Dahisar (1)
Under construction
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Rustomjee 180 Bayview Matunga · 2 phases | Mahim | Mid-construction | Jun 2029 – Dec 2029 | 178 units booked out of total 233 units |
| Rustomjee Aden | Bandra East | Nearing possession | December 2026 | 27 units booked out of 27 units for sale |
| Rustomjee Balmoral · 4 phases | Chembur | Early stage | Apr 2030 – Dec 2030 | 16 units booked out of total 116 units |
| Rustomjee Cliff Tower | Bandra West | Early stage | October 2030 | 5 units booked out of 23 units for sale |
| Rustomjee Crescent | Khar West | Early stage | December 2029 | 33 units booked out of 99 units for sale |
| Rustomjee Crown · 2 phases | Prabhadevi | Ready to move | Dec 2024 – Oct 2027 | 279 units booked out of total 348 units |
| Rustomjee Ocean Vista | Versova | Mid-construction | May 2029 | 20 units booked out of 32 units for sale |
| Rustomjee Ozone Skye | Malad West | Early stage | April 2032 | 0 units booked out of total 128 units |
| Rustomjee Prive | Bandra East | Early stage | November 2029 | 36 units booked out of 56 units for sale |
| Rustomjee Stella | Bandra East | Mid-construction | December 2027 | 75 units booked out of total 89 units |
| Rustomjee Vista Bay | Wadala West | Early stage | January 2031 | 11 units booked out of total 195 units |
| The Panorama By Rustomjee | Bandra West | Nearing possession | October 2028 | 11 units booked out of 14 units for sale |
Completed
| Project | Village | Status |
|---|---|---|
| Erika | Bandra East | Completed |
| Parishram By Rustomjee | Bandra West | Completed |
| Rustomjee Ashiana | Juhu | Completed |
| Rustomjee Cleon | Bandra East | Completed |
| Rustomjee Elements | Andheri West | Completed |
| Rustomjee Paramount | Khar West | Completed |
| Rustomjee Paramount | Santacruz West | Completed |
| Rustomjee Pinnacle | Borivali East | Completed |
| Rustomjee Seasons | Bandra East | Completed |
| Yazarina III | Dadar East | Completed |
| Yazarina One | Dadar East | Completed |
Lapsed
| Project | Village | Status |
|---|---|---|
| Eaze Zone in Laxmi Singh Complex | Malad West | Lapsed |
| Rustomjee Central Park | Andheri East | Lapsed |
| Rustomjee Reserve | Dahisar | Lapsed |
| Rustomjee Summit | Borivali East | Lapsed |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.