Sai Swaroop, Chembur

by Sai Sharan Hotels · Chembur, Mumbai 400071 · Map

Launched
Jun 20243 yrs 6 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
88%Mid-construction
Booked (free sale)
102 of 21547%
Buildings
30.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale102 booked out of 215 units

Land-owner share4 units, not for sale

Total 219 units. Land-owner units are not for sale.

Project facts

1 RK
1
1 BHK
207
2 BHK
8
Other units
3
Total units
219
Buildings
3
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Reserved units
67
Free-sale units
215
Land-owner share (not for sale)
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)88%
Finishes, lifts and services15%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 67%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 70%Jul 2026: Concrete structure (RCC) 85%Oct 2026: Concrete structure (RCC) 88%Dec 2024: Final finishes 0%Dec 2025: Final finishes 10%Jul 2026: Final finishes 10%Oct 2026: Final finishes 15%Excavation 100%Concrete structure (RCC) 88%Final finishes 15%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%88%15%102
100%85%10%67
100%70%10%67
67%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400071

Projects with 100–450 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 6 mths3 yrs 9 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Dec 2027Dec 2027
Concrete structure (RCC)88%94%
Units booked (free sale)47%70%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Sai Swaroop by Sai Sharan Hotels is a 219-unit SRA-sanctioned project in Chembur, Mumbai 400071, launched in June 2024 with possession due in December 2027. 102 units booked out of 215 units for sale. The concrete structure (RCC) is 88% complete.

Read full summary

Sai Swaroop is an SRA-sanctioned project by Sai Sharan Hotels in Chembur, Mumbai 400071, registered with MahaRERA as P51800076721. It was launched in June 2024. It has 219 units in 3 buildings: 216 homes (1 RK, 1 BHK and 2 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 219 units, 215 are for sale and 4 are the land-owner's share, not for sale.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 88% complete, final finishes 15% complete.

102 units booked out of 215 units for sale (47%). Since the July 2026 update, 35 more units have been booked and the reported concrete structure (RCC) has gone from 85% to 88%.