Adityaraj Majestic, Chembur
by Adityaraj Housing LLP · Chembur, Mumbai 400071 · Map
- Launched
- Mar 20243 yrs 9 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 94%Mid-construction
- Booked
- 124 of 17670% · 115 in Jul 2026
- Buildings
- 30.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 134
- 2 BHK
- 30
- Other units
- 12
- Total units
- 176
- Buildings
- 3
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 94% | 0% | 124 | |
| 100% | 81% | 0% | 115 | |
| 100% | 54% | 0% | 87 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400071
Projects with 80–350 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 9 mths | 3 yrs 8 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Dec 2027 |
| Concrete structure (RCC) | 94% | 62% |
| Units booked | 70% | 64% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Gami And Jaydeep Estella, Chembur
- Queens Avenue, Chembur
- Roha Eva Aria, Chembur
- Haware Sky, Chembur
- Sai Swaroop, Chembur
- Queens Glory, Chembur
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Gami And Jaydeep Estella | February 2024 | March 2027 | 100% | 84 units booked out of 122 units for sale |
| Queens Avenue | January 2024 | December 2027 | 0% | 145 units booked out of 161 units for sale |
| Roha Eva Aria | January 2024 | December 2027 | 0% | 69 units booked out of 154 units for sale |
| Haware Sky | June 2024 | February 2029 | 94% | 91 units booked out of total 128 units |
| Sai Swaroop | June 2024 | December 2027 | 88% | 102 units booked out of 215 units for sale |
| Queens Glory | July 2024 | December 2027 | 35% | 107 units booked out of 179 units for sale |
About this project
Adityaraj Majestic by Adityaraj Housing LLP is a 176-unit MHADA-sanctioned project in Chembur, Mumbai 400071, launched in March 2024 with possession due in December 2027. 124 units booked out of total 176 units. The concrete structure (RCC) is 94% complete.
Read full summary
Adityaraj Majestic is a MHADA-sanctioned project by Adityaraj Housing LLP in Chembur, Mumbai 400071, registered with MahaRERA as P51800055402. It was launched in March 2024. It has 176 units in 3 buildings: 164 homes (1 and 2 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 94% complete, final finishes not started.
124 units booked out of total 176 units (70%). Since the July 2026 update, 9 more units have been booked and the reported concrete structure (RCC) has gone from 81% to 94%.
Adityaraj's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 29 |
|---|---|
| Total units across these projects | 3,149 |
| Completed without extending the possession date | 7 |
| Completed after an extension | 2 |
| Lapsed | 10 |
| Under construction | 10 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 3 years 6 months |
| MahaRERA complaints (filed by or against the builder), all Adityaraj projects | 2 (2 of 29 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.