The Altezza, Mulund East

by M/s. VIPL Varasiddhi Infra Project LLP · Mulund East, Mumbai 400081 · Map

Launched
Jun 20245 yrs promised
Possession (MahaRERA)
Jun 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
183 of 29462% · 61 rehab units
Buildings
11.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale183 booked out of 294 units

Rehab61 units for existing members

Total 355 units. Rehab units are not for sale.

Project facts

1 BHK
208
2 BHK
30
3 BHK
93
4 BHK
2
Other units
22
Total units
355
Buildings
1
Land
1.1 acres
Phases
1
MahaRERA complaints
1
Free-sale units
294
Rehab units
61
Reserved units
183

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 0%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%183
0%0%0%183
0%0%0%183
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400081

Projects with 150–700 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400081
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs4 yrs 2 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Jun 2029Dec 2028
Concrete structure (RCC)0%17%
Units booked (free sale)62%77%
MahaRERA complaints (filed by or against the builder)11

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

The Altezza by M/s. VIPL Varasiddhi Infra Project LLP is a 355-unit SRA-sanctioned project in Mulund East, Mumbai 400081, launched in June 2024 with possession due in June 2029. 183 units booked out of 294 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

The Altezza is an SRA-sanctioned project by M/s. VIPL Varasiddhi Infra Project LLP in Mulund East, Mumbai 400081, registered with MahaRERA as P51800076757. It was launched in June 2024. It has 355 units in 1 building: 333 homes (1, 2, 3 and 4 BHK) and 22 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 355 units, 294 are for sale and 61 are rehab units for existing members.

Its registered possession date is June 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

183 units booked out of 294 units for sale (62%).