Nirmiti Seasons, Mulund East
by Nirmiti Enterprises · Mulund East, Mumbai 400081 · Map
- Launched
- Oct 20244 yrs 2 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 96%Mid-construction
- Booked (free sale)
- 101 of 11786% · 40 rehab units
- Buildings
- 20.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale101 booked out of 117 units
Rehab40 units for existing members
Total 157 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 100
- 2 BHK
- 52
- 3 BHK
- 1
- Other units
- 4
- Total units
- 157
- Buildings
- 2
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 117
- Rehab units
- 40
- Reserved units
- 74
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 96% | 0% | 101 | |
| 100% | 91% | 0% | 101 | |
| 100% | 29% | 0% | 97 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400081
Projects with 70–350 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 2 mths | 3 yrs 11 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2028 | Jan 2029 |
| Concrete structure (RCC) | 96% | 0% |
| Units booked (free sale) | 86% | 62% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Silicon Avenue, Mulund East
- Jaydeep Mark, Mulund East
- HS Heritage, Mulund East
- The Altezza, Mulund East
- HS Emerald, Mulund East
- Senroofs Phase IV, Building No D1, Wing A Known As Solana, Mulund East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Silicon Avenue | September 2024 | December 2027 | 0% | 11 units booked out of 69 units for sale |
| Jaydeep Mark | July 2024 | December 2027 | 0% | 80 units booked out of 138 units for sale |
| HS Heritage | February 2025 | March 2029 | 0% | 77 units booked out of 109 units for sale |
| The Altezza | June 2024 | June 2029 | 0% | 183 units booked out of 294 units for sale |
| HS Emerald | March 2025 | December 2028 | 0% | 72 units booked out of 116 units for sale |
| Senroofs Phase IV, Building No D1, Wing A Known As Solana | April 2024 | December 2030 | 17% | 225 units booked out of total 291 units |
About this project
Nirmiti Seasons by Nirmiti Enterprises is a 157-unit SRA-sanctioned project in Mulund East, Mumbai 400081, launched in October 2024 with possession due in December 2028. 101 units booked out of 117 units for sale. The concrete structure (RCC) is 96% complete.
Read full summary
Nirmiti Seasons is an SRA-sanctioned project by Nirmiti Enterprises in Mulund East, Mumbai 400081, registered with MahaRERA as P51800077706. It was launched in October 2024. It has 157 units in 2 buildings: 153 homes (1, 2 and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 157 units, 117 are for sale and 40 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 96% complete, final finishes not started.
101 units booked out of 117 units for sale (86%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 91% to 96%.