Pearl Gardens, Malad West

Ready to move

by Shiv Enterprises · Malad West, Mumbai 400064 · Map

Launched
Jul 20242 yrs 5 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Ready to move
Booked
15 of 2756% · 4 in Dec 2025
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
18
2 BHK
9
Total units
27
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 20%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%15
100%100%20%4
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400064

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400064
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 5 mths2 yrs 10 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Dec 2026Apr 2027
Concrete structure (RCC)100%96%
Units booked56%58%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Pearl Gardens by Shiv Enterprises is a 27-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in July 2024 with possession due in December 2026. 15 units booked out of total 27 units. The concrete structure (RCC) is complete.

Read full summary

Pearl Gardens is a BMC-sanctioned project by Shiv Enterprises in Malad West, Mumbai 400064, registered with MahaRERA as P51800076957. It was launched in July 2024. It has 27 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

15 units booked out of total 27 units (56%). Since the December 2025 update, 11 more units have been booked.