Skip to main content

Milan Mandir Nx, Malad West

by Milan Life Spaces LLP · Malad West, Mumbai 400064 · Map

Launched
Jun 20242 yrs 9 mths promised
Possession (MahaRERA)
Mar 2027Not extended
Concrete structure
93%Mid-construction
Booked (free sale)
10 of 1856% · 22 rehab units
Buildings
20.3 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale10 booked out of 18 units

Rehab22 units for existing members

Total 40 units. Rehab units are not for sale.

Project facts

2 BHK
32
3 BHK
8
Total units
40
Buildings
2
Land
0.3 acres
Phases
1
MahaRERA complaints
1
Free-sale units
18
Rehab units
22

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)93%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 20%Dec 2025: Concrete structure (RCC) 20%Oct 2026: Concrete structure (RCC) 93%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 93%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%93%0%10
100%20%0%6
100%20%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400064

Projects with 20–80 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400064
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 9 mths2 yrs 6 mths
Possession date extendedNo2 of 6
Possession date (MahaRERA)Mar 2027Jun 2027
Concrete structure (RCC)93%100%
Units booked (free sale)56%61%
MahaRERA complaints (filed by or against the builder)10

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Milan Mandir Nx by Milan Life Spaces LLP is a 40-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in June 2024 with possession due in March 2027. 10 units booked out of 18 units for sale. The concrete structure (RCC) is 93% complete.

Read full summary

Milan Mandir Nx is a BMC-sanctioned project by Milan Life Spaces LLP in Malad West, Mumbai 400064, registered with MahaRERA as P51800076809. It was launched in June 2024. It has 40 units in 2 buildings, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 40 units, 18 are for sale and 22 are rehab units for existing members.

Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 93% complete, final finishes not started.

10 units booked out of 18 units for sale (56%). Since the December 2025 update, 4 more units have been booked and the reported concrete structure (RCC) has gone from 20% to 93%.