Rajputana Residency, Goregaon West
by Rajputana Residency LLP · Goregaon West, Mumbai 400104 · Map
- Launched
- Jul 20244 yrs 5 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 75%Mid-construction
- Booked (free sale)
- 14 of 2167% · 6 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale14 booked out of 21 units
Rehab6 units for existing members
Total 27 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 13
- 2 BHK
- 3
- 3 BHK
- 10
- Other units
- 1
- Total units
- 27
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 21
- Rehab units
- 6
- Reserved units
- 11
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 75% | 0% | 14 | |
| 100% | 62% | 0% | 13 | |
| 100% | 0% | 0% | 0 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400104
Projects with 10–60 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 5 mths | 2 yrs 11 mths |
| Possession date extended | No | 0 of 5 |
| Possession date (MahaRERA) | Dec 2028 | Sep 2027 |
| Concrete structure (RCC) | 75% | 100% |
| Units booked (free sale) | 67% | 38% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Building No.9 - Phase II, Goregaon West
- Sanghvi Crystal, Goregaon West
- Bali Primera, Goregaon West
- Ariha One08, Goregaon West
- Bali Serenity, Goregaon West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Building No.9 - Phase II | June 2024 | December 2026 | 70% | 0 units booked out of total 52 units |
| Sanghvi Crystal | October 2024 | February 2028 | 0% | 10 units booked out of 26 units for sale |
| Bali Primera | November 2024 | September 2027 | 100% | 6 units booked out of 9 units for sale |
| Ariha One08 | January 2025 | December 2027 | 100% | 6 units booked out of 16 units for sale |
| Bali Serenity | December 2023 | March 2027 | 100% | 12 units booked out of 13 units for sale |
About this project
Rajputana Residency by Rajputana Residency LLP is a 27-unit SRA-sanctioned project in Goregaon West, Mumbai 400104, launched in July 2024 with possession due in December 2028. 14 units booked out of 21 units for sale. The concrete structure (RCC) is 75% complete.
Read full summary
Rajputana Residency is an SRA-sanctioned project by Rajputana Residency LLP in Goregaon West, Mumbai 400104, registered with MahaRERA as P51800077200. It was launched in July 2024. It has 27 units in 1 building: 26 homes (1, 2 and 3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 27 units, 21 are for sale and 6 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 75% complete, final finishes not started.
14 units booked out of 21 units for sale (67%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 62% to 75%.