- Launched
- Dec 20233 yrs 3 mths promised
- Possession (MahaRERA)
- Mar 2027Not extended
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 12 of 1392% · 31 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale12 booked out of 13 units
Rehab31 units for existing members
Total 44 units. Rehab units are not for sale.
Project facts
- 1 RK
- 1
- 1 BHK
- 13
- 2 BHK
- 26
- Other units
- 4
- Total units
- 44
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 13
- Rehab units
- 31
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 12 | |
| 100% | 100% | 90% | 12 | |
| 100% | 100% | 90% | 12 | |
| 100% | 100% | 30% | 2 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400104
Projects with 20–80 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 3 mths | 3 yrs 7 mths |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Mar 2027 | Dec 2027 |
| Concrete structure (RCC) | 100% | 89% |
| Units booked (free sale) | 92% | 67% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Vogue77, Goregaon West
- Rajputana Residency, Goregaon West
- Bali Primera, Goregaon West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Vogue77 | May 2024 | December 2027 | 89% | 57 units booked out of total 79 units |
| Rajputana Residency | July 2024 | December 2028 | 75% | 14 units booked out of 21 units for sale |
| Bali Primera | November 2024 | September 2027 | 100% | 6 units booked out of 9 units for sale |
About this project
Bali Serenity by Bali Spaces LLP is a 44-unit BMC-sanctioned project in Goregaon West, Mumbai 400104, launched in December 2023 with possession due in March 2027. 12 units booked out of 13 units for sale. The concrete structure (RCC) is complete.
Read full summary
Bali Serenity is a BMC-sanctioned project by Bali Spaces LLP in Goregaon West, Mumbai 400104, registered with MahaRERA as P51800053916. It was launched in December 2023. It has 44 units in 1 building: 40 homes (1 RK, 1 BHK and 2 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 44 units, 13 are for sale and 31 are rehab units for existing members.
Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
12 units booked out of 13 units for sale (92%).