Rudraksh Towers, Mulund West
by Avs Housing And Construction LLP · Mulund West, Mumbai 400080 · Map
- Launched
- Aug 2024First of 2 phases
- Possession (MahaRERA)
- Dec 2029 – Apr 2034Extended in 1 of 2 phases
- Concrete structure
- 25%Weighted across 2 phases
- Booked
- 118 of 18962%
- Buildings
- 22.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 99
- 3 BHK
- 58
- Other units
- 32
- Total units
- 189
- Buildings
- 2
- Land
- 2.2 acres
- Phases
- 2
- MahaRERA complaints
- 0
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Rudraksh Towers Wing B Early stage | P51800077386 | 17 | 0% | 0% | |
| Rudraksh Towers Wing A Mid-construction | P51800077411 | 140 | 28% | 76% |
Show updates by phase
Rudraksh Towers Wing B (P51800077386)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 71% | 0% | 0% | 0 | |
| 71% | 0% | 0% | – | |
| 71% | 0% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Rudraksh Towers Wing A (P51800077411)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 73% | 28% | 0% | 118 | |
| 73% | 0% | 0% | – | |
| 73% | 0% | 0% | – | |
| 0% | 0% | 0% | 41 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 6 similar projects in PIN 400080
Projects with 70–350 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 4 mths | 3 yrs 6 mths |
| Possession date extended | Yes | 0 of 6 |
| Possession date (MahaRERA) | Dec 2029 – Apr 2034 | Jan 2028 |
| Concrete structure (RCC) | 25% | 62% |
| Units booked | 62% | 60% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Alliance Kanchan Krupa, Mulund West
- Ruparel Premia, Mulund West
- Namaha, Mulund West
- Ostwal Gala Kunj, Mulund West
- Om Nandanvan, Mulund West
- Vikas Rise, Mulund West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Alliance Kanchan Krupa | July 2024 | January 2028 | 59% | 19 units booked out of 41 units for sale |
| Ruparel Premia | October 2024 | December 2027 | 64% | 83 units booked out of total 103 units |
| Namaha | November 2024 | Dec 2028 | 0% | 32 units booked out of 120 units for sale |
| Ostwal Gala Kunj | November 2024 | December 2029 | 45% | 60 units booked out of 82 units for sale |
| Om Nandanvan | May 2024 | December 2027 | 95% | 48 units booked out of 58 units for sale |
| Vikas Rise | February 2025 | December 2027 | 80% | 63 units booked out of total 154 units |
About this project
Rudraksh Towers by Avs Housing And Construction LLP is a 189-unit BMC-sanctioned project in Mulund West, Mumbai 400080, registered with MahaRERA in 2 phases, with possession dates from December 2029 to April 2034. 118 units booked out of total 189 units. The concrete structure (RCC) is 25% complete.
Read full summary
Rudraksh Towers is a BMC-sanctioned project by Avs Housing And Construction LLP in Mulund West, Mumbai 400080, registered with MahaRERA as 2 phases (P51800077386, P51800077411). The first phase was launched in August 2024. Together the phases have 189 units in 2 buildings: 157 homes (2 and 3 BHK) and 32 other units (shops, offices or not given by type), as registered with MahaRERA. Both phases are active on MahaRERA.
The phases' registered possession dates run from December 2029 to April 2034; 1 of 2 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 25% complete and final finishes 0% complete. Neither phase has its structure complete.
118 units booked out of total 189 units (62%).