Ostwal Gala Kunj, Mulund West
by Shree Ostwal Builders Ltd · Mulund West, Mumbai 400080 · Map
- Launched
- Nov 20245 yrs 1 mth promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 45%Mid-construction
- Booked (free sale)
- 60 of 8273% · 32 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale60 booked out of 82 units
Rehab32 units for existing members
Total 114 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 65
- 2 BHK
- 10
- 3 BHK
- 22
- 4 BHK
- 2
- Other units
- 15
- Total units
- 114
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 82
- Rehab units
- 32
- Reserved units
- 55
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 45% | 0% | 60 | |
| 100% | 35% | 0% | 73 | |
| 100% | 25% | 0% | 44 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400080
Projects with 40–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 1 mth | 3 yrs 8 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | Dec 2029 | Jun 2028 |
| Concrete structure (RCC) | 45% | 72% |
| Units booked (free sale) | 73% | 52% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Namaha, Mulund West
- Ruparel Premia, Mulund West
- Ambe Ashirwad, Mulund West
- Ratan Laxmi Villa, Mulund West
- Vikas Rise, Mulund West
- Rudraksh Towers, Mulund West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Namaha | November 2024 | Dec 2028 | 0% | 32 units booked out of 120 units for sale |
| Ruparel Premia | October 2024 | December 2027 | 64% | 83 units booked out of total 103 units |
| Ambe Ashirwad | October 2024 | December 2028 | 100% | 23 units booked out of 27 units for sale |
| Ratan Laxmi Villa | January 2025 | December 2026 | 90% | 21 units booked out of 72 units for sale |
| Vikas Rise | February 2025 | December 2027 | 80% | 63 units booked out of total 154 units |
| Rudraksh Towers | August 2024 | Dec 2029 – Apr 2034 | 25% | 118 units booked out of total 189 units |
About this project
Ostwal Gala Kunj by Shree Ostwal Builders Ltd is a 114-unit SRA-sanctioned project in Mulund West, Mumbai 400080, launched in November 2024 with possession due in December 2029. 60 units booked out of 82 units for sale. The concrete structure (RCC) is 45% complete.
Read full summary
Ostwal Gala Kunj is an SRA-sanctioned project by Shree Ostwal Builders Ltd in Mulund West, Mumbai 400080, registered with MahaRERA as P51800077808. It was launched in November 2024. It has 114 units in 1 building: 99 homes (1, 2, 3 and 4 BHK) and 15 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 114 units, 82 are for sale and 32 are rehab units for existing members.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 45% complete, final finishes not started.
60 units booked out of 82 units for sale (73%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 35% to 45%.