Skip to main content

Asian Nirmal, Vile Parle East

by Maniar Asian Infra LLP · Vile Parle East, Mumbai 400057 · Map

Launched
Aug 20243 yrs 10 mths promised
Possession (MahaRERA)
Jun 2028Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
12 of 1771% · 12 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale12 booked out of 17 units

Rehab12 units for existing members

Total 29 units. Rehab units are not for sale.

Project facts

3 BHK
29
Total units
29
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
17
Rehab units
12

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services75%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 75%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 75%Excavation 100%Concrete structure (RCC) 100%Final finishes 75%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%75%12
100%100%0%10
100%75%0%6
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400057

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400057
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 10 mths2 yrs 9 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Jun 2028Jul 2027
Concrete structure (RCC)100%100%
Units booked (free sale)71%56%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Asian Nirmal by Maniar Asian Infra LLP is a 29-unit SRA-sanctioned project in Vile Parle East, Mumbai 400057, launched in August 2024 with possession due in June 2028. 12 units booked out of 17 units for sale. The concrete structure (RCC) is complete.

Read full summary

Asian Nirmal is an SRA-sanctioned project by Maniar Asian Infra LLP in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800077425. It was launched in August 2024. It has 29 units in 1 building, with 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 29 units, 17 are for sale and 12 are rehab units for existing members.

Its registered possession date is June 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 75% complete.

12 units booked out of 17 units for sale (71%). Since the July 2026 update, 2 more units have been booked.