Goyal Atlantis, Vile Parle East
by Graphite Realty · Vile Parle East, Mumbai 400057 · Map
- Launched
- Nov 20242 yrs 8 mths promised
- Possession (MahaRERA)
- Jul 2027Not extended
- Concrete structure
- 40%Mid-construction
- Booked (free sale)
- 2 of 1217% · 15 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale2 booked out of 12 units
Rehab15 units for existing members
Total 27 units. Rehab units are not for sale.
Project facts
- 1 RK
- 6
- 1 BHK
- 7
- 2 BHK
- 7
- 3 BHK
- 4
- Other units
- 3
- Total units
- 27
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 12
- Rehab units
- 15
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 40% | 0% | 2 | |
| 100% | 40% | 0% | 1 | |
| 100% | 0% | 0% | 0 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400057
Projects with 10–50 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 8 mths | 3 yrs 1 mth |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Jul 2027 | Dec 2027 |
| Concrete structure (RCC) | 40% | 100% |
| Units booked (free sale) | 17% | 67% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Rakyan Imperia, Vile Parle East
- Pruthvi Mayur Park, Vile Parle East
- Regent Kashi Kunj, Vile Parle East
- Shanti, Vile Parle East
- Asian Nirmal, Vile Parle East
- Vira Signature, Vile Parle East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Rakyan Imperia | November 2024 | September 2027 | 100% | 18 units booked out of 21 units for sale |
| Pruthvi Mayur Park | November 2024 | March 2028 | 100% | 8 units booked out of 10 units for sale |
| Regent Kashi Kunj | October 2024 | March 2028 | 100% | 14 units booked out of 24 units for sale |
| Shanti | January 2025 | July 2027 | 27% | 5 units booked out of 11 units for sale |
| Asian Nirmal | August 2024 | June 2028 | 100% | 12 units booked out of 17 units for sale |
| Vira Signature | August 2024 | June 2027 | 83% | 10 units booked out of 16 units for sale |
About this project
Goyal Atlantis by Graphite Realty is a 27-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in November 2024 with possession due in July 2027. 2 units booked out of 12 units for sale. The concrete structure (RCC) is 40% complete.
Read full summary
Goyal Atlantis is a BMC-sanctioned project by Graphite Realty in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800077887. It was launched in November 2024. It has 27 units in 1 building: 24 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 27 units, 12 are for sale and 15 are rehab units for existing members.
Its registered possession date is July 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 40% complete, final finishes not started.
2 units booked out of 12 units for sale (17%). Since the July 2026 update, 1 more unit has been booked.