The Vibe, Kandivali West
by Sahakar Builders & Developers · Kandivali West, Mumbai 400067 · Map
- Launched
- Oct 20243 yrs 8 mths promised
- Possession (MahaRERA)
- Jun 2028Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 46 of 6670% · 108 rehab units
- Buildings
- 41.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale46 booked out of 66 units
Rehab108 units for existing members
Total 174 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 2
- 2 BHK
- 95
- 3 BHK
- 28
- 4 BHK
- 17
- Other units
- 32
- Total units
- 174
- Buildings
- 4
- Land
- 1.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 66
- Rehab units
- 108
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 46 | |
| 100% | 38% | 0% | 37 | |
| 80% | 0% | 0% | 26 | |
| 80% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400067
Projects with 70–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 8 mths | 3 yrs 6 mths |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | Jun 2028 | May 2028 |
| Concrete structure (RCC) | 100% | 28% |
| Units booked (free sale) | 70% | 61% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Ambit Primoris, Kandivali West
- Soham Heights, Kandivali West
- Charkop 1 Kaveri Chsl, Kandivali West
- Shreyaan Heights, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ambit Primoris | January 2025 | December 2027 | 0% | 164 units booked out of total 183 units |
| Soham Heights | May 2024 | December 2027 | 56% | 68 units booked out of total 153 units |
| Charkop 1 Kaveri Chsl | March 2025 | September 2028 | 21% | 98 units booked out of 127 units for sale |
| Shreyaan Heights | May 2024 | April 2031 | 36% | 30 units booked out of 144 units for sale |
About this project
The Vibe by Sahakar Builders & Developers is a 174-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in October 2024 with possession due in June 2028. 46 units booked out of 66 units for sale. The concrete structure (RCC) is complete.
Read full summary
The Vibe is a BMC-sanctioned project by Sahakar Builders & Developers in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800077570. It was launched in October 2024. It has 174 units in 4 buildings: 142 homes (1, 2, 3 and 4 BHK) and 32 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 174 units, 66 are for sale and 108 are rehab units for existing members.
Its registered possession date is June 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.
46 units booked out of 66 units for sale (70%). Since the July 2026 update, 9 more units have been booked and the reported concrete structure (RCC) has gone from 38% to 100%.