Skip to main content

Charkop 1 Kaveri Chsl, Kandivali West

by Jadeite Developers LLP · Kandivali West, Mumbai 400067 · Map

Launched
Mar 20253 yrs 6 mths promised
Possession (MahaRERA)
Sep 2028Not extended
Concrete structure
21%Mid-construction
Booked (free sale)
98 of 12777% · 41 rehab units
Buildings
20.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale98 booked out of 127 units

Rehab41 units for existing members

Total 168 units. Rehab units are not for sale.

Project facts

1 BHK
89
2 BHK
76
Other units
3
Total units
168
Buildings
2
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
127
Rehab units
41

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)21%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 14%Oct 2026: Concrete structure (RCC) 21%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 21%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%21%0%98
100%14%0%–
0%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400067

Projects with 80–350 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 6 mths3 yrs 10 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Sep 2028Nov 2028
Concrete structure (RCC)21%14%
Units booked (free sale)77%57%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Charkop 1 Kaveri Chsl by Jadeite Developers LLP is a 168-unit MHADA-sanctioned project in Kandivali West, Mumbai 400067, launched in March 2025 with possession due in September 2028. 98 units booked out of 127 units for sale. The concrete structure (RCC) is 21% complete.

Read full summary

Charkop 1 Kaveri Chsl is a MHADA-sanctioned project by Jadeite Developers LLP in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800079902. It was launched in March 2025. It has 168 units in 2 buildings: 165 homes (1 and 2 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 168 units, 127 are for sale and 41 are rehab units for existing members.

Its registered possession date is September 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 21% complete, final finishes not started.

98 units booked out of 127 units for sale (77%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 14% to 21%.