Skip to main content

Pratham - By Shraddha, Borivali East

by Shraddha Prime Projects Limited · Borivali East, Mumbai 400066 · Map

Launched
Oct 20245 yrs 2 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
0%Early stage
Booked
–
Buildings
10.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Total units
–
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation90%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 90%Oct 2026: Excavation 90%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 90%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
90%0%0%–
90%0%0%–
0%0%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Pratham - By Shraddha by Shraddha Prime Projects Limited is a MHADA-sanctioned project in Borivali East, Mumbai 400066, launched in October 2024 with possession due in December 2029. Work on the concrete structure (RCC) has not started.

Read full summary

Pratham - By Shraddha is a MHADA-sanctioned project by Shraddha Prime Projects Limited in Borivali East, Mumbai 400066, registered with MahaRERA as P51800077622. It was launched in October 2024. Its MahaRERA status is Active.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation 90% complete, structure (RCC) not started, final finishes not started.

Shraddha's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA53
Total units across these projects9,707
Completed without extending the possession date16
Completed after an extension4
Lapsed5
Under construction28
Possession date extended on the builder's application18
Typical time from launch to 100% structure4 years
MahaRERA complaints (filed by or against the builder), all Shraddha projects14 (11 of 53 projects)

See all Shraddha projects →