Skip to main content

Avalon, Juhu

by V Hotels Ltd · Juhu, Mumbai 400049 · Map

Launched
Nov 2024First of 2 phases
Possession (MahaRERA)
Sep 2028Not extended
Concrete structure
100%Weighted across 2 phases
Booked
15 of 2658% · 12 in Jul 2026
Buildings
20.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

5+ BHK
22
Other units
4
Total units
26
Buildings
2
Land
0.3 acres
Phases
2
MahaRERA complaints
0

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Avalon - Tower A
Nearing possession
P5180007786211100%62%
Avalon - Tower B
Nearing possession
P5180007966911100%54%
Show updates by phase

Avalon - Tower A (P51800077862)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%8
100%45%0%7
100%0%0%8
0%0%0%0

"–" means MahaRERA shows no figure for that update.

Avalon - Tower B (P51800079669)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%7
100%39%0%5
100%0%0%0

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 42%Oct 2026: Concrete structure (RCC) 100%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

How to read construction stages

Compared with 4 similar projects in PIN 400049

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400049
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 8 mths4 yrs 2 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Sep 2028Jan 2029
Concrete structure (RCC)100%44%
Units booked58%36%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Avalon by V Hotels Ltd is a 26-unit SRA-sanctioned project in Juhu, Mumbai 400049, registered with MahaRERA in 2 phases, with possession due in September 2028. 15 units booked out of total 26 units. The concrete structure (RCC) is complete.

Read full summary

Avalon is an SRA-sanctioned project by V Hotels Ltd in Juhu, Mumbai 400049, registered with MahaRERA as 2 phases (P51800077862, P51800079669). The first phase was launched in November 2024. Together the phases have 26 units in 2 buildings: 22 homes (5+ BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Both phases are active on MahaRERA.

The registered possession date is September 2028; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 0% complete. Both phases have their structure complete.

15 units booked out of total 26 units (58%). Since the July 2026 update, 3 more units have been booked.