Astoria, Juhu

by Avishkar Keval Kunj Redevelopment Private Limited · Juhu, Mumbai 400049 · Map

Launched
Dec 20243 yrs 5 mths promised
Possession (MahaRERA)
May 2028Not extended
Concrete structure
88%Mid-construction
Booked (free sale)
5 of 1631% · 14 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale5 booked out of 16 units

Rehab14 units for existing members

Total 30 units. Rehab units are not for sale.

Project facts

2 BHK
2
3 BHK
26
4 BHK
2
Total units
30
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
16
Rehab units
14

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)88%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 10%Oct 2026: Concrete structure (RCC) 88%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 88%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%88%0%5
100%10%0%4
100%0%0%2
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400049

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400049
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 5 mths4 yrs 10 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)May 2028Oct 2029
Concrete structure (RCC)88%0%
Units booked (free sale)31%45%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Astoria by Avishkar Keval Kunj Redevelopment Private Limited is a 30-unit MHADA-sanctioned project in Juhu, Mumbai 400049, launched in December 2024 with possession due in May 2028. 5 units booked out of 16 units for sale. The concrete structure (RCC) is 88% complete.

Read full summary

Astoria is a MHADA-sanctioned project by Avishkar Keval Kunj Redevelopment Private Limited in Juhu, Mumbai 400049, registered with MahaRERA as P51800078441. It was launched in December 2024. It has 30 units in 1 building, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 30 units, 16 are for sale and 14 are rehab units for existing members.

Its registered possession date is May 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 88% complete, final finishes not started.

5 units booked out of 16 units for sale (31%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 10% to 88%.