Bag-E-Noor CHSL, Malad East
by Mozaic Homes (India) LLP · Malad East, Mumbai 400097 · Map
- Launched
- Nov 20243 yrs 4 mths promised
- Possession (MahaRERA)
- Mar 2028Not extended
- Concrete structure
- 63%Mid-construction
- Booked (free sale)
- 7 of 3619% · 60 rehab units
- Buildings
- 21.4 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale7 booked out of 36 units
Rehab60 units for existing members
Total 96 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 69
- 2 BHK
- 22
- 3 BHK
- 5
- Total units
- 96
- Buildings
- 2
- Land
- 1.4 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 36
- Rehab units
- 60
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 63% | 10% | 7 | |
| 100% | 87% | 0% | 7 | |
| 100% | 61% | 0% | 7 | |
| 75% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400097
Projects with 40–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 4 mths | 4 yrs 4 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Mar 2028 | Dec 2028 |
| Concrete structure (RCC) | 63% | 18% |
| Units booked (free sale) | 19% | 2% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 6 projects
- Sheetal Shree Ram Kunj, Malad East
- Blue Zone, Malad East
- Shreeji Tapovan, Malad East
- Construction of Bldg on Plot CTS No 104 J Pt and 147 Pt of S.No 31 and 39, Old Dindoshi, Malad East, Malad East
- Proposed Bldg on Plot CTS No. 827 B, S.No. 239, in betn Shivneri CHS MCGM Pumphouse, Khadakpada, Malad East
- Mehta Highland 1978, Malad East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sheetal Shree Ram Kunj | November 2024 | December 2029 | 35% | 16 units booked out of 40 units for sale |
| Blue Zone | November 2024 | March 2030 | 0% | 0 units booked out of 120 units for sale |
| Shreeji Tapovan | October 2024 | December 2028 | 0% | 0 units booked out of 60 units for sale |
| Construction of Bldg on Plot CTS No 104 J Pt and 147 Pt of S.No 31 and 39, Old Dindoshi, Malad East | August 2024 | September 2025 | 100% | – |
| Proposed Bldg on Plot CTS No. 827 B, S.No. 239, in betn Shivneri CHS MCGM Pumphouse, Khadakpada | August 2024 | September 2025 | 80% | – |
| Mehta Highland 1978 | July 2024 | December 2028 | 0% | 5 units booked out of total 134 units |
About this project
Bag-E-Noor CHSL by Mozaic Homes (India) LLP is a 96-unit BMC-sanctioned project in Malad East, Mumbai 400097, launched in November 2024 with possession due in March 2028. 7 units booked out of 36 units for sale. The concrete structure (RCC) is 63% complete.
Read full summary
Bag-E-Noor CHSL is a BMC-sanctioned project by Mozaic Homes (India) LLP in Malad East, Mumbai 400097, registered with MahaRERA as P51800077944. It was launched in November 2024. It has 96 units in 2 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 96 units, 36 are for sale and 60 are rehab units for existing members.
Its registered possession date is March 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 63% complete, final finishes 10% complete.
7 units booked out of 36 units for sale (19%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 87% to 63%.