Construction of Bldg on Plot CTS No 104 J Pt and 147 Pt of S.No 31 and 39, Old Dindoshi, Malad East, Malad East

Lapsed

by Mumbai Housing And Area Development Board · Malad East, Mumbai 400097 · Map

Launched
Aug 20241 yr 1 mth promised
Possession (MahaRERA)
Sep 2025Not extendedWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
–
Buildings
10.3 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
89
Total units
89
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services25%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 25%Dec 2025: Final finishes 25%Jul 2026: Final finishes 25%Oct 2026: Final finishes 25%Excavation 100%Concrete structure (RCC) 100%Final finishes 25%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%25%–
100%100%25%–
100%100%25%–
100%100%25%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400097

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400097
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 1 mth4 yrs 4 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Sep 2025Dec 2028
Concrete structure (RCC)100%18%
Units booked–12%
MahaRERA complaints (filed by or against the builder)10

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Construction of Bldg on Plot CTS No 104 J Pt and 147 Pt of S.No 31 and 39, Old Dindoshi, Malad East by Mumbai Housing And Area Development Board is an 89-unit project in Malad East, Mumbai 400097, launched in August 2024; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

Construction of Bldg on Plot CTS No 104 J Pt and 147 Pt of S.No 31 and 39, Old Dindoshi, Malad East is a project by Mumbai Housing And Area Development Board in Malad East, Mumbai 400097, registered with MahaRERA as P51800077312. It was launched in August 2024. It has 89 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in September 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 25% complete.