The Marque, Bandra West

by Gurukrupa Realcon Infrabuild LLP · Bandra West, Mumbai 400050 · Map

Launched
Nov 20243 yrs 11 mths promised
Possession (MahaRERA)
Oct 2028Not extended
Concrete structure
38%Mid-construction
Booked (free sale)
10 of 3033% · 46 rehab units
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale10 booked out of 30 units

Rehab46 units for existing members

Total 76 units. Rehab units are not for sale.

Project facts

2 BHK
21
3 BHK
23
4 BHK
31
5+ BHK
1
Total units
76
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
30
Rehab units
46

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)38%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 10%Jul 2026: Concrete structure (RCC) 33%Oct 2026: Concrete structure (RCC) 38%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 38%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%38%0%10
100%33%0%5
100%10%0%3
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400050

Projects with 30–200 flats, launched within 1 year of this one.

Compared with 6 similar projects in PIN 400050
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 11 mths3 yrs 7 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Oct 2028May 2028
Concrete structure (RCC)38%0%
Units booked (free sale)33%81%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

The Marque by Gurukrupa Realcon Infrabuild LLP is a 76-unit MHADA-sanctioned project in Bandra West, Mumbai 400050, launched in November 2024 with possession due in October 2028. 10 units booked out of 30 units for sale. The concrete structure (RCC) is 38% complete.

Read full summary

The Marque is a MHADA-sanctioned project by Gurukrupa Realcon Infrabuild LLP in Bandra West, Mumbai 400050, registered with MahaRERA as P51800078233. It was launched in November 2024. It has 76 units in 1 building, with 2, 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 76 units, 30 are for sale and 46 are rehab units for existing members.

Its registered possession date is October 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 38% complete, final finishes not started.

10 units booked out of 30 units for sale (33%). Since the July 2026 update, 5 more units have been booked and the reported concrete structure (RCC) has gone from 33% to 38%.

Gurukrupa Realcon's track record in Mumbai

MahaRERA projects registered 2019–2026 in Mumbai

Projects registered with MahaRERA25
Total units across these projects2,757
Completed without extending the possession date10
Completed after an extension2
Lapsed3
Under construction10
Possession date extended on the builder's application2
Typical time from launch to 100% structure2 years 9 months
MahaRERA complaints (filed by or against the builder), all Gurukrupa Realcon projects3 (3 of 25 projects)

See all Gurukrupa Realcon projects →