Silverbay, Bandra West
by Shraddha Shelters Pvt Ltd · Bandra West, Mumbai 400050 · Map
- Launched
- Mar 20243 yrs 9 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 47 of 7761% · 28 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale47 booked out of 77 units
Rehab28 units for existing members
Total 105 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 87
- Other units
- 18
- Total units
- 105
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 77
- Rehab units
- 28
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 47 | |
| 100% | 0% | 0% | 47 | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400050
Projects with 40–200 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 9 mths | 3 yrs 11 mths |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Dec 2027 | Oct 2028 |
| Concrete structure (RCC) | 0% | 38% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- St Anthony Chs, Bandra West
- Noori Horizon, Bandra West
- The Marque, Bandra West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| St Anthony Chs | February 2024 | March 2026 | 70% | – |
| Noori Horizon | July 2024 | December 2029 | 0% | 2 units booked out of total 99 units |
| The Marque | November 2024 | October 2028 | 38% | 10 units booked out of 30 units for sale |
About this project
Silverbay by Shraddha Shelters Pvt Ltd is a 105-unit BMC-sanctioned project in Bandra West, Mumbai 400050, launched in March 2024 with possession due in December 2027. 47 units booked out of 77 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Silverbay is a BMC-sanctioned project by Shraddha Shelters Pvt Ltd in Bandra West, Mumbai 400050, registered with MahaRERA as P51800055163. It was launched in March 2024. It has 105 units in 1 building: 87 homes (2 BHK) and 18 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 105 units, 77 are for sale and 28 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.
47 units booked out of 77 units for sale (61%).
Shraddha's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 53 |
|---|---|
| Total units across these projects | 9,707 |
| Completed without extending the possession date | 16 |
| Completed after an extension | 4 |
| Lapsed | 5 |
| Under construction | 28 |
| Possession date extended on the builder's application | 18 |
| Typical time from launch to 100% structure | 4 years |
| MahaRERA complaints (filed by or against the builder), all Shraddha projects | 14 (11 of 53 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.