SEERon Dyo, Malad West
by Amrapali Heights Co Op Housing Society Ltd · Malad West, Mumbai 400064 · Map
- Launched
- Dec 20242 yrs 6 mths promised
- Possession (MahaRERA)
- Jun 2027Not extended
- Concrete structure
- 59%Mid-construction
- Booked (free sale)
- 16 of 2370% · 55 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale16 booked out of 23 units
Rehab55 units for existing members
Total 78 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 38
- 2 BHK
- 28
- 3 BHK
- 1
- Other units
- 11
- Total units
- 78
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 23
- Rehab units
- 55
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 59% | 25% | 16 | |
| 100% | 59% | 25% | 13 | |
| 100% | 59% | 0% | 11 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400064
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 6 mths | 3 yrs 1 mth |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Jun 2027 | Nov 2027 |
| Concrete structure (RCC) | 59% | 60% |
| Units booked (free sale) | 70% | 57% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Alfred Splendour, Malad West
- Acres Abode, Malad West
- Rishab Aangan, Malad West
- Vir Paradise, Malad West
- Redevelopment Of Glendon Chsl, Sheldon Chsl, Orlem Luciana Chsl, Malad West
- Shreeji Bliss, Malad West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Alfred Splendour | January 2025 | December 2027 | 70% | 32 units booked out of total 70 units |
| Acres Abode | February 2025 | February 2027 | 100% | 23 units booked out of 43 units for sale |
| Rishab Aangan | March 2025 | June 2028 | 60% | 13 units booked out of 19 units for sale |
| Vir Paradise | March 2025 | November 2027 | 13% | 87 units booked out of 105 units for sale |
| Redevelopment Of Glendon Chsl, Sheldon Chsl, Orlem Luciana Chsl | July 2024 | November 2027 | 60% | 40 units booked out of 66 units for sale |
| Shreeji Bliss | July 2024 | January 2028 | 31% | 37 units booked out of 90 units for sale |
About this project
SEERon Dyo by Amrapali Heights Co Op Housing Society Ltd is a 78-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in December 2024 with possession due in June 2027. 16 units booked out of 23 units for sale. The concrete structure (RCC) is 59% complete.
Read full summary
SEERon Dyo is a BMC-sanctioned project by Amrapali Heights Co Op Housing Society Ltd in Malad West, Mumbai 400064, registered with MahaRERA as P51800078353. It was launched in December 2024. It has 78 units in 1 building: 67 homes (1, 2 and 3 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 78 units, 23 are for sale and 55 are rehab units for existing members.
Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 59% complete, final finishes 25% complete.
16 units booked out of 23 units for sale (70%). Since the July 2026 update, 3 more units have been booked.