by Jkd Engineers And Infrastructure Private Limited · Malad West, Mumbai 400064 · Map

Launched
Mar 20252 yrs 8 mths promised
Possession (MahaRERA)
Nov 2027Not extended
Concrete structure
13%Mid-construction
Booked (free sale)
87 of 10583% · 52 rehab units
Buildings
20.5 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale87 booked out of 105 units

Rehab52 units for existing members

Total 157 units. Rehab units are not for sale.

Project facts

1 BHK
75
2 BHK
22
3 BHK
19
4 BHK
1
Other units
40
Total units
157
Buildings
2
Land
0.5 acres
Phases
1
MahaRERA complaints
1
Free-sale units
105
Rehab units
52
Reserved units
75

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)13%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 6%Oct 2026: Concrete structure (RCC) 13%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 13%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%13%0%87
100%6%0%86
100%0%0%84

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400064

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400064
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 8 mths2 yrs 8 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Nov 2027Sep 2027
Concrete structure (RCC)13%65%
Units booked (free sale)83%58%
MahaRERA complaints (filed by or against the builder)10

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Vir Paradise by Jkd Engineers And Infrastructure Private Limited is a 157-unit SRA-sanctioned project in Malad West, Mumbai 400064, launched in March 2025 with possession due in November 2027. 87 units booked out of 105 units for sale. The concrete structure (RCC) is 13% complete.

Read full summary

Vir Paradise is an SRA-sanctioned project by Jkd Engineers And Infrastructure Private Limited in Malad West, Mumbai 400064, registered with MahaRERA as P51800079526. It was launched in March 2025. It has 157 units in 2 buildings: 117 homes (1, 2, 3 and 4 BHK) and 40 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 157 units, 105 are for sale and 52 are rehab units for existing members.

Its registered possession date is November 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 13% complete, final finishes not started.

87 units booked out of 105 units for sale (83%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 6% to 13%.