Elite Homes, Jogeshwari West
by Massif Infrastructure Developers · Jogeshwari West, Mumbai 400102 · Map
- Launched
- Dec 20245 yrs promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 68%Mid-construction
- Booked (free sale)
- 41 of 19221% · 143 rehab units
- Buildings
- 20.7 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale41 booked out of 192 units
Rehab143 units for existing members
Total 335 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 278
- 2 BHK
- 40
- Other units
- 17
- Total units
- 335
- Buildings
- 2
- Land
- 0.7 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 192
- Rehab units
- 143
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 68% | 50% | 41 | |
| 100% | 68% | 50% | 41 | |
| 50% | 15% | 0% | 0 | |
| 50% | 15% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400102
Projects with 150–700 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs | 5 yrs |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | Dec 2029 | Jan 2030 |
| Concrete structure (RCC) | 68% | 6% |
| Units booked (free sale) | 21% | 60% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Mega Residency, Jogeshwari West
- Pearl Providence, Jogeshwari West
- Veena Insignia, Jogeshwari West
- A H Atlantis, Jogeshwari West
- Pearl Blossom, Jogeshwari West
- The Westpark, Jogeshwari West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Mega Residency | December 2024 | December 2029 | 0% | – |
| Pearl Providence | November 2024 | December 2029 | 53% | 113 units booked out of 187 units for sale |
| Veena Insignia | October 2024 | March 2030 | 10% | 46 units booked out of 133 units for sale |
| A H Atlantis | February 2025 | December 2030 | 0% | 0 units booked out of total 194 units |
| Pearl Blossom | June 2024 | December 2028 | 100% | 265 units booked out of total 291 units |
| The Westpark | June 2025 | Jun 2032 – Jun 2034 | 3% | 407 units booked out of total 553 units |
About this project
Elite Homes by Massif Infrastructure Developers is a 335-unit SRA-sanctioned project in Jogeshwari West, Mumbai 400102, launched in December 2024 with possession due in December 2029. 41 units booked out of 192 units for sale. The concrete structure (RCC) is 68% complete.
Read full summary
Elite Homes is an SRA-sanctioned project by Massif Infrastructure Developers in Jogeshwari West, Mumbai 400102, registered with MahaRERA as P51800078458. It was launched in December 2024. It has 335 units in 2 buildings: 318 homes (1 and 2 BHK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 335 units, 192 are for sale and 143 are rehab units for existing members.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 68% complete, final finishes 50% complete.
41 units booked out of 192 units for sale (21%).