Veena Insignia, Jogeshwari West
by Veena Infratech LLP · Jogeshwari West, Mumbai 400102 · Map
- Launched
- Oct 20243 yrs 5 mths originally promised
- Possession (MahaRERA)
- Mar 2030Extended by 2 yrs
- Concrete structure
- 10%Mid-construction
- Booked (free sale)
- 46 of 13335% · 84 rehab units
- Buildings
- 10.7 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale46 booked out of 133 units
Rehab84 units for existing members
Total 217 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 102
- 3 BHK
- 102
- 4 BHK
- 2
- Other units
- 11
- Total units
- 217
- Buildings
- 1
- Land
- 0.7 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 133
- Rehab units
- 84
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 10% | 0% | 46 | |
| 100% | 10% | 0% | 30 | |
| 100% | 0% | 0% | 6 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400102
Projects with 100–450 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 5 mths | 5 yrs |
| Possession date extended | By 2 yrs | 0 of 5 |
| Possession date (MahaRERA) | Mar 2030 | Dec 2029 |
| Concrete structure (RCC) | 10% | 53% |
| Units booked (free sale) | 35% | 41% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Pearl Providence, Jogeshwari West
- Mega Residency, Jogeshwari West
- Elite Homes, Jogeshwari West
- A H Atlantis, Jogeshwari West
- Pearl Blossom, Jogeshwari West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Pearl Providence | November 2024 | December 2029 | 53% | 113 units booked out of 187 units for sale |
| Mega Residency | December 2024 | December 2029 | 0% | – |
| Elite Homes | December 2024 | December 2029 | 68% | 41 units booked out of 192 units for sale |
| A H Atlantis | February 2025 | December 2030 | 0% | 0 units booked out of total 194 units |
| Pearl Blossom | June 2024 | December 2028 | 100% | 265 units booked out of total 291 units |
About this project
Veena Insignia by Veena Infratech LLP is a 217-unit MHADA-sanctioned project in Jogeshwari West, Mumbai 400102, launched in October 2024 with possession due in March 2030. 46 units booked out of 133 units for sale. The concrete structure (RCC) is 10% complete.
Read full summary
Veena Insignia is a MHADA-sanctioned project by Veena Infratech LLP in Jogeshwari West, Mumbai 400102, registered with MahaRERA as PM1180002400053. It was launched in October 2024. It has 217 units in 1 building: 206 homes (2, 3 and 4 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 217 units, 133 are for sale and 84 are rehab units for existing members.
Its registered possession date is March 2030, extended by 2 years from the original March 2028. Construction: excavation complete, structure (RCC) 10% complete, final finishes not started.
46 units booked out of 133 units for sale (35%). Since the July 2026 update, 16 more units have been booked.
Veena's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 15 |
|---|---|
| Total units across these projects | 2,186 |
| Completed without extending the possession date | 6 |
| Completed after an extension | 2 |
| Lapsed | 1 |
| Under construction | 6 |
| Possession date extended on the builder's application | 4 |
| Typical time from launch to 100% structure | 4 years 2 months |
| MahaRERA complaints (filed by or against the builder), all Veena projects | 19 (7 of 15 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.