Om Sonal Heights, Ghatkopar West

by D. D. Dezines Group · Ghatkopar West, Mumbai 400086 · Map

Launched
Jan 20252 yrs 9 mths promised
Possession (MahaRERA)
Oct 2027Not extended
Concrete structure
12%Mid-construction
Booked (free sale)
17 of 2277% · 29 rehab units
Buildings
20.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale17 booked out of 22 units

Rehab29 units for existing members

Total 51 units. Rehab units are not for sale.

Project facts

1 BHK
8
2 BHK
10
3 BHK
17
Other units
16
Total units
51
Buildings
2
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
22
Rehab units
29

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)12%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 7%Jul 2026: Concrete structure (RCC) 12%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 12%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%12%0%17
100%7%0%14
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400086

Projects with 10–70 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400086
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 9 mths3 yrs 6 mths
Possession date extendedNo1 of 4
Possession date (MahaRERA)Oct 2027Jun 2028
Concrete structure (RCC)12%45%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Om Sonal Heights by D. D. Dezines Group is a 51-unit BMC-sanctioned project in Ghatkopar West, Mumbai 400086, launched in January 2025 with possession due in October 2027. 17 units booked out of 22 units for sale. The concrete structure (RCC) is 12% complete.

Read full summary

Om Sonal Heights is a BMC-sanctioned project by D. D. Dezines Group in Ghatkopar West, Mumbai 400086, registered with MahaRERA as P51800078689. It was launched in January 2025. It has 51 units in 2 buildings: 35 homes (1, 2 and 3 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 51 units, 22 are for sale and 29 are rehab units for existing members.

Its registered possession date is October 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 12% complete, final finishes not started.

17 units booked out of 22 units for sale (77%).